ARTICLE · 30 DECEMBER 2021

What (SOPA claims) are you getting for Christmas?

Holding Redlich
Holding Redlich
Contributor
Holding Redlich

Holding Redlich

Holding Redlich is a large national commercial firm with offices in Melbourne, Canberra, Sydney,...

View firm profile
Explore more from Holding Redlich

Principals and head contractors should be aware of the tight timeframes to respond to these payment claims.

AustraliaReal Estate and Construction

The Building and Construction Industry Security of Payment Act 1999 (NSW) (Act) provides a mechanism for making claims for payment and quickly determining disputes about payment, on an interim basis, by adjudication. Disputes can be determined through to payment in as little as 45 days.

With the object of keeping payments flowing in the construction industry, the framework of the Act requires various steps to be taken in the payment claim and adjudication processes within five or 10 business days. Those time periods are not extendable.

In the early years of the Act, claimants were known to ambush respondents with payment claims at Christmas, hoping they would be overlooked during the holiday break and become payable as a debt, regardless of merit.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

This publication does not deal with every important topic or change in law and is not intended to be relied upon as a substitute for legal or other advice that may be relevant to the reader's specific circumstances. If you have found this publication of interest and would like to know more or wish to obtain legal advice relevant to your circumstances please contact one of the named individuals listed.