ARTICLE · 11 SEPTEMBER 2023

Understanding provisional sum and prime cost items in building contracts

All parties to a building contract should understand how these clauses operate before the contract is signed.

AustraliaReal Estate and Construction

Provisional sum and prime cost items are allowances made for works, materials or labour that can't be adequately quantified when a building contract is entered into. They allow a construction project to progress while the unknown amount is being determined. As these items can result in significant increases in the contract price, it's important that all parties to a building contract understand how these clauses operate before the contract is signed.

What is a provisional sum?

In most fixed price building contracts, a situation may arise where particular building materials and labour costs cannot be properly calculated at the time of finalising the contract. The provisional sum items enable the parties to estimate the cost of those works, rather than waiting until the amounts can be determined. Once the relevant work is done, the difference between the actual costs of the work and the allowance given in the provisional sum will be deducted or applied to the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from