ARTICLE · 16 JULY 2024

The Effect Of Nominal Rates For Liquidated Damages

This article discusses the impact of the statutory warranties under section 18B of the Home Building Act 1989 (NSW) (HBA) on liquidated damages under a construction contract.

AustraliaReal Estate and Construction

Not an exhaustive remedy for a delay

This article discusses the impact of the statutory warranties under section 18B of the Home Building Act 1989 (NSW) (HBA) on liquidated damages under a construction contract.

Introduction

Generally, liquidated pre-ascertained damages are an express agreement between the parties of the genuine pre-estimate of the loss and damage suffered by a party in the event the other party fails to complete by the date for completion.

There has always been a presumption that when a liquidated damages provision exists in a construction contract, it is the intention of the parties that liquidated damages are the sole monetary remedy for a failure to complete by the date for completion.1 This may no longer be the case for a residential construction contract where the statutory warranties under the HBA are implied.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from