In Walton Construction (Qld) Pty Ltd v Corrosion Control
Technology Pty Ltd & Ors [2011] QSC 67 (Walton
v CCT), DibbsBarker acted for a contractor in setting
aside an adjudication decision made in favour of a subcontractor.
The case identified an important constraint on the operation of the
Building and Construction Industry Payments Act 2004 (Qld)
(BCIPA), being that upon a contract being
terminated, no further "reference dates" arise for the
purposes of BCIPA.
The recent case of McNab NQ Pty Ltd v Walkrete Pty Ltd &
Ors [2013] QSC 128 (McNab case)
makes it clear that the benefit of the decision in Walton v CCT is
available to other contractors. To that end, if a contract permits,
a contractor's valid termination of a subcontract will have the
effect of extinguishing a subcontractor's ability to
successfully use