The recent Supreme Court of NSW decision by Ball J in Fairfield City Council v Abergeldie Contractors Pty Ltd1 (Abergeldie)...

AustraliaReal Estate and Construction

The recent Supreme Court of NSW decision by Ball J in Fairfield City Council v Abergeldie Contractors Pty Ltd1 (Abergeldie), provides another demonstration of how issues with reference dates2 can provide potent grounds for challenging determinations under the Building and Construction Industry Security of Payment Act 1999 (Act).

In Abergeldie:

  1. The contract was based on an amended version of the widely used AS4000-1997 general conditions (Contract) and included:
    1. clause 37.1, providing that a progress claim may be made on the 28th of each month for "Works under the Contract" done to the 28th day of that month,
    2. a clause 44 providing that for the purpose of section 8(2) of the Act3, only one payment claim could be made immediately after practical completion on "the first date for a progress claim arising immediately after practical completion (as determined under subclause 37.1)"4.