ARTICLE · 21 JULY 2020

Schedule Of Rates Or Lump Sum? Pick Your Poison

On 29 May 2020, the New South Wales Court of Appeal (Court of Appeal) handed down its decision in C&V Engineering Pty Ltd v Hamilton & Marino Builders Pty Ltd [2020] NSWCA 103.

AustraliaReal Estate and Construction

On 29 May 2020, the New South Wales Court of Appeal (Court of Appeal) handed down its decision in C&V Engineering Pty Ltd v Hamilton & Marino Builders Pty Ltd [2020] NSWCA 103. The case deals with a common dispute in construction supply contracts: whether the contract is a 'schedule of rates contract' or a 'lump sum contract'.

Facts

Hamilton & Marino Builders Pty Ltd (Builder) was engaged to construct a 55-unit development which required the supply and installation of 'plates' and 'angles'.

The Builder requested C&V Engineering Pty Ltd (Supplier) to provide a quote for the plates and angles. At the time, the actual number of plates and angles required for the development was uncertain and the Supplier provided a quote for the supply and installation of 1,000 plates and angles, (arguably) a lump sum contract.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from