Litigants in breach of warranty claims, should be aware that rectification of defective work is the preferred outcome.

AustraliaReal Estate and Construction

Work orders vs money orders – to and from the preferred outcome

Litigants in breach of statutory warranty claims must be aware of the overarching principle, established in section 48MA of the Home Building Act 1989 (NSW) (Act), that the NSW Civil and Administrative Tribunal (Tribunal) must have regard to the principle that rectification of the defective work by the responsible party is the preferred outcome.

Unsurprisingly, owners by and large seek money orders, whereas builders seek work orders. For a money order, the Tribunal must be satisfied that the making of a work order would be inappropriate. Harding v Horticultural Holdings Pty Ltd [2022] NSWCATCD 22 adds to the decisions which have given guidance on the application of that principle.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

This publication does not deal with every important topic or change in law and is not intended to be relied upon as a substitute for legal or other advice that may be relevant to the reader's specific circumstances. If you have found this publication of interest and would like to know more or wish to obtain legal advice relevant to your circumstances please contact one of the named individuals listed.

See more popular content from