In this edition we look at two new disciplinary case studies published by the Building Professionals Board (BPB), concerning in each instance the conduct of a principal certifying authority (PCA).

PCA work carried out without formal appointment

The BPB reprimanded a certifier and issued him a $3000 fine after he issued a complying development certificate (CDC) without formal appointment as the PCA. The certifier believed that he was acting appropriately and helping the owner in circumstances of unauthorised development, however, in doing so he failed to convey the seriousness of not formally appointing a PCA.

Section 109D(2) of the Environmental Planning and Assessment Act 1979 (EPA Act) prohibits the issue of an occupation certificate except by the PCA and s 109E(1) of the EPA Act requires the person with the benefit of the CDC to appoint a PCA before work commences. The certifier was in breach of s 85(2) of the Building Professionals Act 2005 by