We summarise cases & other news on residential property matters.

AustraliaReal Estate and Construction

Little v J & K Homes Pty Ltd [2017] NSWCATAP 84

The NCAT Appeal Panel considered an appeal by the Owners that the Tribunal had erred in dismissing their claim for defects on the basis that the building contract remained on foot.

At first instance, the Tribunal below relied on Brewarrina Shire Council v Beckhaus Civil Pty Ltd & 1 Or [2005] NSWCA 248 (the Brewarrina Case) to find that the owners did not have standing to bring proceedings for breach of statutory warranties for defective works where the contract had not yet been terminated.

The Tribunal below referred to the leading judgement of Ipp JA (Hodgson and McColl JJA agreeing) which states:

"While on this assumption (the Contract still being on foot), the Council may have been entitled to claim damages for delay arising out of Beckhaus' failure to achieve practical completion by the date for practical completion, it could not sue Beckhaus for defective or incomplete works... This situation would have