In brief - Andrews v ANZ to have significant impact on drafting of construction contracts

Whether or not a payment is triggered by a breach of contract, it may still be classified as a penalty. However, if the party liable to make the payment cannot prove that it was not a genuine pre-estimate of loss, it would not be classified as a penalty.

Landmark judgment widens definition of penalties

In September 2012 the High Court handed down a landmark judgement in the case of Andrews v ANZ. This decision has paved the way for a wider range of fees to be categorised as penalties.

The High Court held that a fee or other sum that is payable on the occurrence or non-occurrence of an event may still be characterised as a penalty, even if the event itself is not a breach of contract. (For more information please see our earlier article Andrews v ANZ revives equitable jurisdiction concerning relief against penalties.)