Share on LinkedInShare on LinkedIn

ARTICLE · 26 SEPTEMBER 2019

NSW Independent Planning Commission refuses development consent for Bylong Valley coal mine

Corrs Chambers Westgarth
Corrs Chambers Westgarth
Contributor
Corrs Chambers Westgarth

Corrs Chambers Westgarth

Corrs Chambers Westgarth is Australia’s leading independent law firm. We provide exceptional legal...

View firm profile
Explore more from Corrs Chambers Westgarth

The case highlights challenges of approving new mines in areas of particular scenic, cultural and heritage significance.

AustraliaReal Estate and Construction

A recent decision by the NSW Independent Planning Commission (IPC), in which it refused development consent for the Bylong Valley Coal Mine (Project), highlights the challenges involved with having new mines approved in areas of particular scenic, cultural and heritage significance.

The refusal came on 18 September 2019, despite the NSW Department of Planning, Industry and Environment (DPIE) recommending approval and the proponent having revised its mine plan to address concerns raised in a Review Report prepared by the IPC's predecessor, the Planning Assessment Commission (PAC).

The IPC cited long-lasting environmental, agricultural and heritage impacts as the main reasons for refusal. In a statement that referred extensively to the Land and Environment Court's judgment in Gloucester Resources Ltd v Minister for Planning [2019] NSWLEC 7 (Rocky Hill), the IPC stated that the proponent had not done enough to minimise greenhouse gas (GHG) emissions associated with

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

    Lawyers Weekly Law firm of the year 2021                  
Employer of Choice for Gender Equality (WGEA)

See more popular content from