No liquidated damages? No problem (unless you're a builder)

Even if a contract states that no liquidated damages are payable for delay, the party may still claim damages at common law.

AustraliaReal Estate and Construction

Key Points:

Even if a contract states that no liquidated damages are payable to a party for a delay, that party may still be entitled to claim damages at common law.

A court will not readily accept an argument by a contractor that the parties intended to exclude a claim for damages for delay without clear words to that effect. In the recent case of Adapt Constructions Pty Ltd v Whittaker [2015] ACTSC 188, the ACT Supreme Court found that a construction contract based on a standard form which left blank the amount for liquidated damages to be paid for delays to completion did not prevent the principal to the contract from recovering unliquidated damages at common law for that delay.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from