Since 2017 there has been a rapid withdrawal of professional
indemnity insurance capacity from the Australian market, both in
the construction sector and generally. The withdrawal has come
after a sustained period of unprofitability that has been
exacerbated by external events including a Royal Commission into
the banking sector and the combustible cladding crisis.
There has been a 40% reduction in capacity from the Lloyd's
market alone. In the construction sector, this has led to large
increases in premiums, reductions in the overall aggregate limit of
insurance policies, limits on specific claims, and the application
of "cladding exclusions".
Cladding assessment and remediation