Liquidated damages in construction contracts: Enforceability and common disputes

Holding Redlich
Holding Redlich
Contributor
Holding Redlich

Holding Redlich

Holding Redlich is a large national commercial firm with offices in Melbourne, Canberra, Sydney,...

View firm profile
Explore more from Holding Redlich

Factors that affect the legal enforceability of these clauses and common disputes between principals and contractors over its application.

AustraliaReal Estate and Construction

Project delays are a common challenge in many construction projects across Australia. These delays not only push back the original practical completion date but also lead to disputes over financial repercussions and the legitimacy of the delay itself. For parties involved in a project, it is crucial to understand how liquidated damages clauses operate and the disputes it can trigger.

A liquidated damages clause represents a pre-agreed mechanism by which the contractor compensates the principal for failing to complete the project by the agreed date for practical completion. It offers a predictable way to manage delays without requiring the principal to prove actual damages in court and provides contractors with clear visibility of their potential liability for late completion.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

This publication does not deal with every important topic or change in law and is not intended to be relied upon as a substitute for legal or other advice that may be relevant to the reader's specific circumstances. If you have found this publication of interest and would like to know more or wish to obtain legal advice relevant to your circumstances please contact one of the named individuals listed.

See more popular content from