ARTICLE · 01 AUGUST 2011

Limitation period for Victorian building actions

Discussion of Brirek Industries Case, where County Court of Victoria adopted a more limited reading of s 134 of the Building Act 1993.

AustraliaReal Estate and Construction

Brirek Industries Pty Limited v McKenzie Group Consulting (Vic) Pty Limited [2011] VCC 294

Introduction

In this case, the County Court of Victoria has adopted a more limited reading of the scope of s134 of the Building Act 1993 (Vic) ('the Building Act'), concerning the limitation period for building actions, than earlier decisions of the Victorian Civil and Administrative Tribunal ('VCAT'). It is the first court (as opposed to VCAT) decision, of which we are aware, dealing with the scope of the section.

The issues

Section 134 of the Building Act provides as follows:

'Despite anything to the contrary in the Limitation of Actions Act 1958 or in any other Act or law, a building action cannot be brought more than 10 years after the date of issue of the Occupancy Permit in respect of the building work (whether or not the Occupancy Permit is subsequently cancelled or varied) or, if an Occupancy Permit is not issued, the date of issue under Part V of the