ARTICLE · 27 OCTOBER 2012

Epc Contracts For Wind Energy Projects - South African Re Ipp Programme - Lessons Learned From Phases 1 And 2 (October 2012) Part 6

Information on drafting EPC contracts.

AustraliaReal Estate and Construction

KEY GENERAL CLAUSES IN EPC CONTRACTS

Delay and Extensions of Time

The Prevention Principle

As noted previously, one of the advantages of an EPC Contract is that it provides the project company with a fixed completion date. If the contractor fails to complete the works by the required date they are liable for DLDs. However, in some circumstances the contractor is entitled to an extension of the date for completion. Failure to grant an extension for a project company caused delay can void the liquidated damages regime and 'set time at large'. This means the contractor is only obliged to complete the works within a reasonable time.

This is the situation under common law governed contracts due to the prevention principle. The prevention principle was developed by the courts to prevent employers i.e.: project companies from delaying contractors and then claiming DLDs.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from