1.2.2 Electrical System Tests

Commissioning Tests shall be performed on all items of the Wind Farm electrical system, in accordance with the standards of a Reasonable and Prudent Operator, the standard procedures of the Contractor and the requirements of this Contract, and shall include (but not be limited to) the following:

  1. Wind Turbine transformers:
    1. Check mechanical state and earth connections.
    2. Check satisfactory equipment labelling.
    3. Check tap selector switch in correct position.
  1. Substation transformers:
    1. Ratio measurement on all tap settings.
    2. Winding resistance measurement on highest, lowest and nominal tap settings.
    3. Insulation resistance between all windings, and each winding to earth;