Congratulations! You have just obtained an adjudication certificate. What comes next if the respondent refuses to pay the adjudicated amount?

AustraliaReal Estate and Construction

Congratulations! You have just obtained an adjudication certificate. What comes next if the respondent refuses to pay the adjudicated amount? Knowing how to enforce SOPA debts is essential for construction industry participants who want to exercise their right to receive progress payment.

Two potentially powerful options available to claimants are Statutory Demands and Garnishee Orders.

Adjudication Determinations

Once the adjudicator determines the amount of the progress payment owing, the respondent is bound to pay the adjudicated amount within five business days after the date on which the adjudication determination was served on the respondent.1

If the respondent fails to pay the adjudicated amount on time, the claimant is entitled to suspend construction work and request an adjudication certificate.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from