E-ALERT: Everything old is new again?: reference dates and payment claims in a construction contract

A reference date is re-established as a precondition to the making of a valid payment claim in a construction contract.

AustraliaReal Estate and Construction

As was widely anticipated, on 21 December 2016, the High Court unanimously allowed the appeal in Southern Han Breakfast Point Pty Ltd (in Liquidation) v Lewence Construction Pty Ltd [2016] HCA 52 and firmly re-established the previously accepted view that a reference date is a precondition to the making of a valid payment claim under the Building and Construction Industry Security of Payment Act 1999 (NSW) (Act)1.

Brief history of the matter

Southern Han entered into a construction contract with Lewence. The contract provided that payment claims were to be made on the 8th date of each month. The contract also allowed Southern Han to take the work out of Lewence's hands in certain circumstances of unremedied default. The same clause allowed Southern Han to suspend payments in the event that it took the works out of Lewence's hands.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from