These long-awaited BCIPA changes dramatically alter the landscape for payment claims and adjudications in Queensland.

AustraliaReal Estate and Construction

The long-awaited changes to the Building and Construction Industry Payments Act 2004 (Qld) (BCIPA) commenced on 15 December 2014, dramatically altering the landscape for payment claims and adjudications in Queensland.

A number of significant changes have been implemented.

Importantly, there is a new regime for the categorisation of payment claims. Payment claims for less than $750,000 (excluding GST) are categorised as 'standard' payment claims, which a respondent must respond to within 10 business days or the time required under the construction contract.

Where the claim is for over $750,000 (excluding GST) it will be categorised as a 'complex' payment claim and the respondent will have an extended time to respond (either 15 business days, 30 business days or the time required under the construction contract – depending on the provisions of the contract and when the payment claim was served).