This was an appeal against a refusal by the Respondent (Council) to grant development permits to the Appellant (Westlink).

AustraliaReal Estate and Construction

Download the judgement

Appeal - Application for a Development Permit – Conflict – Extent of Conflict – Sufficient Grounds to Justify Approval of Proposal Despite Conflict – s 3.5.14(2)(b) Integrated Planning Act 1997 – South East Queensland Regional Plan 2009 - 2031 – Gatton Planning Scheme.

Facts: This was an appeal against a refusal by the Respondent (Council) to grant development permits to the Appellant (Westlink) for:

  1. material change of use - electricity generation infrastructure; and
  2. environmentally Relevant Activity (ERA) no. 14 – electricity generation; and
  3. operational works – vegetation clearing.

The subject site was located within the Rural General Zone under the provisions of the Planning Scheme for Gatton Shire (Planning Scheme) and was located in close proximity to the Gatton Gas and Compressor Station, the Gatton Electrical Bulk Supply Substation and the Roma to Brisbane Gas Pipeline.