What are the next steps in the Pindan insolvency?

There are many challenges arising out of the Pindan Constructions insolvency.

AustraliaInsolvency/Bankruptcy/Re-Structuring

WHAT ARE THE NEXT STEPS IN THE PINDAN INSOLVENCY?

Pindan Constructions' insolvency has left major construction works unfinished and about 500 subcontractors owed payment for work they have done across Pindan's 68 pending projects.

Pindan's external administrators, EY, are left with the task of finding a way to get as many projects finished and subcontractors paid as possible. And they will need to move quickly because unfinished building sites cost money just to maintain.

If those works were financed as is typical, the owners will keep on losing money by servicing loans and diluting their capital investment.

It is even worse for those who have made time-sensitive commitments to customers or investors. Consider, for example, off-the-plan apartment buyers who have planned to move in or rent out their new apartment by a certain date. Other kinds of projects will have similar problems with clients left in limbo. Disappointed investors will inevitably lose money and

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from