Introduction
A number of recent and ongoing Australian PPP projects have and continue to face significant delays and financial distress. Notable examples include Victoria’s Ararat Prison and Desalination Plant projects. This sort of distress on PPP projects invariably leads to disputes and is, as a result, very damaging both for the individual projects and for the future of major public infrastructure projects more generally.
To assist in avoiding problems leading to disputes, we believe that governments should consider including dispute boards (DBs) on PPPs. For a number of years DBs have been used successfully in major projects in Queensland and NSW1. In our view, DBs could also be helpful for PPPs, with the appropriate modifications to cater for the complex structure of these projects. Recently, this view has received support from the chair of Infrastructure NSW, Nick Greiner2.