The case interpreted 'termination for convenience' and 'entire agreement' clauses in Defence contracts and subcontracts.

AustraliaGovernment, Public Sector
Adrian D'Amico
Adrian D'Amico
Nick Beresford-Wylie
Nick Beresford-Wylie
Author LinkedIn connections

In BAE Systems Australia Ltd v Cubic Defence New Zealand Ltd [2011] FCA 1434, the Federal Court was required to consider whether a purported 'termination for convenience' of only part of a Subcontract was valid. The Court also considered whether or not certain implied terms could be excluded by the use of an 'entire agreement' clause.

Background

The respondent, a defence contractor, entered into a contract (the Prime Contract) with the Department of Defence for the supply, operation, support and maintenance of certain information and simulation systems for a training program. It subsequently entered into a contract with the applicant (the Subcontract) for the provision of supplies and support services in relation to the program.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from