Government Update: Liquidated Damages in Government Contracts

The Full Court of the Supreme Court of Tasmania has upheld an appeal by the State of Tasmania against the first instance decision of the then Chief Justice Cox in the State’s multi-million dollar dispute with Leighton Contractors.

AustraliaGovernment, Public Sector
Jessica Dickerson
Jessica Dickerson

Discussed in State of Tasmania v Leighton Contractors Pty Ltd [2005] TASSC 33

The Full Court of the Supreme Court of Tasmania has upheld an appeal by the State of Tasmania against the first instance decision of the then Chief Justice Cox in the State’s multi-million dollar dispute with Leighton Contractors.

In November 2004, Cox CJ ruled that the liquidated damages imposed under a construction contract between the parties were a penalty and therefore unenforceable. The State was ordered to repay Leighton nearly $2.5 million which had been withheld pursuant to the liquidated damages clause.

The State appealed and, shortly before Christmas last year, the Full Court overturned the decision, ruling in favour of the State.