Key Points:
The North West Rail Link PPP is proving to be a
pioneering one: its use of a Dispute Avoidance Board, and its
breakthrough on outsourcing determinations.
Dispute Avoidance Boards (DABs) are an effective mechanism to
avoid and resolve disputes on major infrastructure projects, but up
until now they haven't been used on a PPP project in Australia,
or perhaps anywhere. This has now changed with the adoption of a
DAB on the North West Rail Link PPP, on which we advised –
and along the way, we found a way to deal with one of the few
drawbacks of DABs.
What are DABs?
Usually three independent people are appointed to form the DAB
by the owner and the contractor at the start of a project to solve
problems that arise during construction. They'll typically
have, between them, significant experience in delivering similar
projects and project-related dispute resolution – a blend of
engineering, project management and legal expertise.