So, you've rebuilt your renewable energy power station. Are you eligible for more Renewable Energy Certificates?

Renovating a renewable energy power station didn't alter change the power station's eligibility to create RECs.

AustraliaEnvironment

Key Points:

Renovating a renewable energy power station didn't alter change the power station's eligibility to create renewable energy certificates.

Don't assume you can clear out a generating baseline for renewable energy certificates (RECs), and create more RECs, just because you have redeveloped your power station.

In a rare decision under the Renewable Energy (Electricity) Act 2000 (Cth), the Administrative Appeals Tribunal (AAT) has decided that a recent $500M renovation and re-construction of a pulp mill and biomass power station do not change the power station's eligibility to create renewable energy certificates (RECs), and has reimposed its 1997 renewable power baseline. This means that the power station will create RECS only for the electricity it generates above its 1997 baseline, despite the renovation works.