Key Points:
Queensland's Environmental Protection Act has been
amended to provide additional tools to respond to emergency
releases of water.
During the 2010/11 wet season, many Queensland mines and other
facilities were forced to release excess water, some of it water
that was considered contaminated.
With the wet season again approaching, it is appropriate to
consider the various mechanisms available under the Environmental
Protection Act 1994 (Qld) (EP Act) to authorise the release of
excess water from licensed sites, including mines, industrial and
manufacturing sites.
Since the 2010/11 wet season, and in response to the Queensland
Floods Commission of Inquiry, the State has amended the EP Act to
provide additional tools to respond to emergency releases of water.
While some of these amendments have taken effect already, others
are imminent. Relevant mechanisms to consider for a release
include: