ARTICLE · 24 JULY 2025

Market Intelligence Thought Leadership Award Winner

Transforming Queensland's Energy Landscape

Herbert Smith Freehills Kramer LLP
Herbert Smith Freehills Kramer LLP
Contributor
Herbert Smith Freehills Kramer LLP

Herbert Smith Freehills Kramer LLP

We have one of the largest Southeast Asia international law practices, working across the region...

View firm profile
Explore more from Herbert Smith Freehills Kramer LLP

The amendments mean that for development applications for material change of use for a wind farm or a large-scale solar farm (defined as having a maximum instantaneous electricity...

AustraliaEnergy and Natural Resources

The Queensland Parliament has now passed the Planning (Social Impact and Community Benefit) and Other Legislation Amendment Bill 2025 which introduces further legislative reforms impacting the renewable energy industry in Queensland. The amendments commenced on 18 July 2025.

The amendments mean that for development applications for material change of use for a wind farm or a large-scale solar farm (defined as having a maximum instantaneous electricity output of 1MW or more, or being located in a priority development area):

  • it is a pre-condition to lodging a development application that a social impact assessment (SIA) has been completed and a community benefits agreement (CBA) has been entered into between the developer and the relevant local government(s) (and potentially others), unless the chief executive gives notice that this is not required. The cost of this is borne wholly by proponents;

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from