Is It A Power Pole Or Part Of A Telecoms Network? Multiple Use Poles And The Law

an electricity utility's pole on which telecommunications facilities are installed does not thereby become a "facility" (a tower) for the purposes of the Telecommunications Act, even if the utility has replaced a pole to support the telecommunications facilities

AustraliaEnergy and Natural Resources

Key Points

  • an electricity utility's pole on which telecommunications facilities are installed does not thereby become a "facility" (a tower) for the purposes of the Telecommunications Act, even if the utility has replaced a pole to support the telecommunications facilities;
    • this means that the poles are still subject to State laws (such as planning law);the High Court adopted an "element by element" analysis of whether the facilities were low-impact (rather than aggregating the facilities on, or associated with, a site together);
    • it also considered a Facilities Access Agreement and the nature of the arrangements made between the parties under that Agreement.

    A recent decision of the High Court in Hutchison 3G Australia v City of Mitcham [2006] HCA 12 considers the definition of a "facility" under the provisions of Schedule 3 to the Telecommunications Act 1997 (Cth) ("Telco Act") and the interaction between Schedule 3 and State government planning and development