When are parties bound by an expert determination clause in a construction contract?

Cooper Grace Ward
Cooper Grace Ward
Contributor
Cooper Grace Ward

Cooper Grace Ward

Cooper Grace Ward was established in 1980 and has quickly become one of the largest independent...

View firm profile
Explore more from Cooper Grace Ward

In Lipman Pty Limited v. Emergency Services Superannuation Board [2010] NSWSC 710, the New South Wales Supreme Court held that an expert determination made under a construction contract was binding on the parties.

AustraliaCorporate/Commercial Law

In Lipman Pty Limited v. Emergency Services Superannuation Board [2010] NSWSC 710, the New South Wales Supreme Court held that an expert determination made under a construction contract was binding on the parties.

The facts

Lipman, as principal, retained Emergency Services Superannuation Board to redevelop a shopping centre near Sydney.

The contract required the parties to refer disputes for expert determination. It also provided that the expert determination would be final and binding unless and until it was "reversed, overturned or otherwise changed" under a specific negotiation procedure provided for in the conract.

The contractual negotiation procedure enabled a party dissatisfied with the expert determination to issue a notice of appeal. This notice of appeal triggered a requirement for the executives of the parties to meet and undertake negotiations with a view to resolving the dispute (or trying to agree upon a process to resolve the dispute).