Share on LinkedInShare on LinkedIn

ARTICLE · 17 AUGUST 2005

Federal Appeals Court Holds That Challenges to Corps of Engineers Wetlands Permit Regulations Are Ripe for Review

In a big win for aggregates companies and for public agencies that build transportation and water resource projects, the U.S. Court Appeals for the District of Columbia Circuit, on July 29, 2005, reversed a lower court decision finding that their challenge to the U.S. Army Corps of Engineers (Corps) 2002 Nationwide Permit Regulations (NWP) under the federal Clean Water Act was final agency action and, therefore, "ripe for review."

United StatesEnvironment
Rafe Petersen
Rafe Petersen

By Lawrence R. Liebesman and Rafe Peterson (Washington, D.C.)

Originally published 3rd Quarter 2005

In a big win for aggregates companies and for public agencies that build transportation and water resource projects, the U.S. Court Appeals for the District of Columbia Circuit, on July 29, 2005, reversed a lower court decision finding that their challenge to the U.S. Army Corps of Engineers (Corps) 2002 Nationwide Permit Regulations (NWP) under the federal Clean Water Act was final agency action and, therefore, "ripe for review." The aggregates industry and public agencies had challenged numerous provisions in the NWP regulations, particularly focusing on NWP 43 for storm water management and NWP 44 for mining, asserting that these NWPs were essentially useless given the severe restrictions on floodplain impacts and the one-half acre national cap in wetlands impacts. In November 2003, Judge Richard Leon refused to address the merits, finding that the NWP regulations were not final

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from