ARTICLE · 16 FEBRUARY 2022

10 Key Changes In The CCDC 2 (2020)

This article highlights 10 key changes that owners, contractors, and consultants should be aware of in the CCDC 2.

CanadaReal Estate and Construction

The CCDC 2 (2008) will be pulled off the shelf in June 2022 and officially replaced with the CCDC 2 (2020). This article highlights 10 key changes that owners, contractors, and consultants should be aware of in the CCDC 2 (2020).

1. READY-FOR-TAKEOVER MILESTONE

Ready-for-Takeover ("RFT") is a new scheduling milestone concept related to the completion of the project. It is intended to be a mechanism to ensure the timely total completion of the project once substantial performance has been achieved.

RFT is in addition to, and does not replace, Substantial Performance, and, importantly, does not replace Substantial Performance as a trigger for the release of the holdback. This new milestone is important in connection with the following contractual terms and provisions: Contract Time; Indemnity; Warranty; Waiver; and Delay.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from