From July 15, 2023, construction of new coal-fired and gas-turbined power plants that are unable to meet a specific energy efficiency rate will no longer be allowed.

VietnamEnergy and Natural Resources

A. NEW STANDARDS FOR COAL-FIRED AND GAS-TURBINE POWER PLANTS

From July 15, 2023, construction of new coal-fired and gas-turbined power plants that are unable to meet a specific energy efficiency rate will no longer be allowed. The minimum energy efficiency rate of each power generation unit must exceed the minimum efficiency rate set out in Decision 14/2023/QD-TTg of the Prime Minister dated May 24, 2023 ("Decision 14").

Subject to technology and capacity, the minimum efficiency rate may vary. Below are the mandated minimum efficiency rates under Decision 14:

No Power generation unit Minimum Efficiency Rate (%)
I. Coal fired plants
1 Capacity ≥ 50 MW and < 150 MW

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from