The New National Power Development Plan Of Vietnam

The Prime Minister has recently issued the long-awaited Decision 500, approving the national power development plan ("PDP8"). Decision 500 took effect on May 15, 2023.

VietnamEnergy and Natural Resources

The Prime Minister has recently issued the long-awaited Decision 500, approving the national power development plan ("PDP8"). Decision 500 took effect on May 15, 2023. It covers a term of 27 years (2023 to 2050). It provides general policies, objectives, plans for development of power generation and transmission lines, land use, list of important projects, and a general road map to implement PDP8. This Article is a highlight and analysis of general policies set out in PDP8.

Background and general observations. In 2021, the Ministry of Industry and Trade ("MOIT") submitted its proposal1 and a draft of the national power development plan ("2021 Version") for the period from 2020 to 2030 (with a vision up to 2050) to the Prime Minister for his approval. The 2021 Version contained 1,000 pages and 19 Chapters that provided assessments, plans for several important industry matters (eg, performance review, forecast, power generation, development and diversion of various

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from