Introduction
We start with Decision 500/QD-TTg of Vietnam's Prime
Minister on "Approving National Electricity Development
Planning for 2021-2030 and Vision for 2050" (aka PDP
VIII). No new coal-fired thermal power plants will be
approved after 2030, and no new LNG power plants will be approved
after 2035. The objective is to develop renewable energy power
plants, and thus to make the transition from coal
to biomass and ammonia energy.
For projects that utilize LNG, the objective is to
make the transition to hydrogen fuel, when hydrogen technology is
commercialized and the market price is appropriate.
At present, Vietnam has limited ability to supply energy from
biomass and green ammonia; thus there is no guarantee for long-term
supply and stable operation. In addition, the commercial-scale
production of green ammonia is very costly, and this makes the path
towards "replacing coal energy with ammonia and biomass
energy" long and uncertain.