Contractor Entitled To Due Process Hearing Before Its Bid Is Rejected As Nonresponsive
Sedgwick Detert Moran & Arnold
In D.H. Williams Construction Inc., v. Clovis Unified School District (Emmett's Excavation, Inc.), (C.D.O.S. 401 (January 10, 2007)), the California Court of Appeals held that a public agency could not reject the lowest bid as nonresponsive based upon the lowest bidding contractor listing an unlicensed subcontractor on bid forms.