In Vic Davis Construction, Inc. v. Lauren Engineers &
Constructors, Inc., the Tennessee Court of Appeals approved a
contractor’s use of closeout costs to “holdback”
5% of the contract price without complying with the retainage
requirements of the Prompt Pay Act.
The subcontractor alleged that the general contractor withheld a
percentage of payment in a line item that was designated as
“Turn-over, As-Builts, Final Cleanup, Demobilize.” The
subcontractor noted not only that the amount of this line item
($108,835.00) equaled five percent (5%) of the total contract price
but also that $108,835.00 was not representative of the cost of
“Turn-over, As-Builts, Final Cleanup, Demobilize” as it
related to the subcontractor’s scope of work on the project.
The subcontractor claimed that such work would cost less than
$20,000.00. What is more, at trial, the subcontractor’s
project manager testified that the general contractor referred to
these amounts as “holdback” in