ARTICLE · 11 AUGUST 2014

The Unrecognized Sole-Source Requirement: A Lesson In Failing To Understand The Specifications

The CBCA denied a contractor's claims for defective specifications when the performance specification at issue created a sole-source requirement.

United StatesGovernment, Public Sector

In the recent decision of CMEC/ARC Electric JV v. Dep't of Veterans Affairs, the Civilian Board of Contract Appeals (CBCA) denied a contractor's claims for defective specifications when the performance specification at issue created a sole-source requirement.

The appeal involved a contract to replace and upgrade generators at the Spokane VA Medical Center. The contract included a performance specification to install a digital HVAC control system. Importantly, the specification required that one database be used to operate the entire system. After the award of the contract, the contractor identified a solution that would utilize two separate databases. The VA rejected this solution, and the contractor submitted a request for equitable adjustment (REA) on the grounds that the requirement for a single database amounted to a sole-source requirement. In essence, the contractor argued that because only one control system would work under the specification, it was entitled

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from