This month's Law360 Bid Protest Roundup focuses on one recent U.S. Court of Federal Claims decision, as well as two Government Accountability Office (GAO) decisions.

United StatesGovernment, Public Sector

This month's Law360 Bid Protest Roundup focuses on one recent U.S. Court of Federal Claims decision, as well as two Government Accountability Office (GAO) decisions. All three involve solicitations issued by the Department of Veterans Affairs (VA), but each serves as a different, important reminder for disappointed offerors seeking to have their own protests sustained.

Land Shark Shredding1

In Land Shark Shredding, an instructive case for government contractors regarding the impact transactions can have on pending protests, the Court of Federal Claims dismissed a protest for lack of standing because the party bringing the protest was not a valid successor-in-interest to the party that submitted the proposal at issue.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

Because of the generality of this update, the information provided herein may not be applicable in all situations and should not be acted upon without specific legal advice based on particular situations.