In its recent decision in Air Tractor, Inc., the
Government Accountability Office (GAO) held that the Department of
Defense (DoD) may, at its own discretion, begin a project with
agreements under its prototyping Other Transaction (OT) authority,
and award later phases of the same project on a sole source basis
under its experimental purchasing authority. In the decision, GAO
discussed distinctions between these avenues, and gave a broad
reading to the DoD's authority to award contracts for
experimental work.1
Introduction
The past few years have seen a swell of interest in DoD's
ability to sidestep the Federal Acquisition Regulation (FAR) and
use more flexible OT authority to enter into contracts.2
Thus far, the majority of this interest has centered on DoD's
OT authority to enter into prototype projects, now codified at 10
U.S.C. § 2371b. One of the most powerful features of DoD's
prototype OT authority is that DoD may award a sole source
follow-on production