A Landmark Decision in the Ruta del Sol Arbitration Against ANI
Provides Valuable Lessons for Developers and Financiers of Projects
in Latin America
The landmark decision in the Ruta del Sol arbitration against
the Agencia Nacional de Infraestructura – ANI, the
Colombian government agency in charge of awarding concessions
through public-private partnerships for the design, construction,
maintenance, operation and administration of transport
infrastructure in Colombia, addresses the key issue of whether
governments must honor termination payments when the award of a
concession or governmental agreement was tainted by corruption
during the awarding process. In this landmark decision, the
Arbitral Tribunal awarded the termination payments notwithstanding
its declaration that the agreement was null and void, but did so
(i) only in favor of those parties who had been unaware of the
unlawful acts and who had acted in good faith and without fault
(for example, the