ARTICLE · 01 FEBRUARY 2024

New Lawsuit Challenges Funding For Delta Water Tunnel

Sheppard
Sheppard
Contributor
Sheppard

Sheppard

Businesses turn to Sheppard to deliver sophisticated counsel to help clients move ahead. With more...

View firm profile
Explore more from Sheppard

The complaint alleges that the state violated the California Environmental Quality Act (CEQA) when it approved the project in December 2023.

United StatesEnvironment

The Daily Journal reports that the California Department of Water Resources is facing a legal challenge from numerous environmental groups in Sacramento County Superior Court for the Delta Conveyance Project, a $16 billion project to build a 36 feet wide, 45 miles long, and 150 feet deep tunnel under the Sacramento-San Joaquin Delta. The complaint alleges that the state violated the California Environmental Quality Act (CEQA) when it approved the project in December 2023.

Sheppard Mullin Real State, Energy, Land Use & Environmental partner Alex Merritt commented to the Daily Journal that "the CEQA requires the agency to study a reasonable range of alternatives that could mitigate the environmental impact of an undertaking, which [will be] a big issue in the case going forward." He added that "the lawsuit is a 'pretty' standard CEQA petition and the department will likely have to convince the court through its administrative record that it has complied with

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from