FERC Affirms Its Environmental Analysis In Columbia's East Side Expansion Project

On October 14, 2015, FERC issued an order ("October 14 Order") denying rehearing and stay of its December 18, 2014 order...

United StatesEnvironment

On October 14, 2015, FERC issued an order ("October 14 Order") denying rehearing and stay of its December 18, 2014 order ("December 18 Order") authorizing Columbia Gas Transmission, LLC ("Columbia") to construct and operate its East Side Expansion Project and abandon facilities that will be replaced as part of the project.  In the October 14 Order, FERC found that it had fully addressed environmental issues raised by the Clean Air Council and the Allegheny Defense Project ("Allegheny") in its environmental assessment ("EA") and the December 18 Order.

Columbia proposed to construct and operate the East Side Expansion Project to increase firm transportation service on the Columbia system by 312,000 dekatherms to serve the mid-Atlantic and northeast markets.  The project would involve looping existing pipelines; replacing compressors at the Milford and Easton Compressor Stations; and installing various measurement, station piping, valves, and appurtenant facilities at

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from