ARTICLE · 11 JANUARY 2023

Federal Court Ruling Could Raise The Bar For Proving Causation Under CERCLA

Without widespread alarm, the United States District Court for the Central District of California rejected a plaintiff's claim this past October for reimbursement of millions of dollars in the CERCLA...

United StatesEnvironment

Without widespread alarm, the United States District Court for the Central District of California rejected a plaintiff's claim this past October for reimbursement of millions of dollars in the CERCLA cost-recovery case, California Department of Toxic Substances Control v. NL Industries, Inc., ___ F. Supp. 3d ___, No 2:20-CV-11293-SVW-JPR, 2022 WL 14769903 (C.D. Cal. Oct. 20, 2022). The implications of this decision, however, could echo loudly in future CERCLA cost-recovery actions, as the decision defines a new standard for establishing the causation prong in such an action.

Background

In NL Industries, the remediation costs stem from lead contamination from a former Exide plant near Los Angeles, where lead-acid batteries were recycled for more than 100 years. The cleanup area extends 1.7 miles around the plant. The immediate 0.5-mile radius is an industrial area, while the remaining cleanup area is residential. The California Department of Toxic

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.