ARTICLE · 02 AUGUST 2026

PJM Board Directs FERC Filing On Reliability Backstop Procurement And Interim Resource Adequacy Service

PJM's Board of Managers has directed the filing of proposals for a Reliability Backstop Procurement and Interim Resource Adequacy Service with FERC, following an intensive stakeholder process to address resource adequacy threats in the region. The proposals include a Large Load Registry, procurement mechanisms beginning in September 2026, and new requirements for large customers without sufficient capacity as of June 1, 2027.

United StatesEnergy and Natural Resources

On July 27, the PJM Board of Managers issued a “decisional letter” that directed PJM to file proposals for a Reliability Backstop Procurement and Connect and Manage—renamed “Interim Resource Adequacy Service”—with FERC in the next few days. This letter follows an intensive stakeholder process that explored ways to address the resource adequacy threats in the region. The key elements of PJM’s proposal are:

  • A “Large Load Registry,” which will be maintained by PJM and is intended to improve load forecasts and support the Reliability Backstop Procurement and Interim Resource Adequacy Service. “Large Load” is defined as an end-use customer with a peak load of 50 MW or more at a single point of interconnection or multiple points of interconnection within a one-mile radius.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from