In Great Britain as in many international markets, a wave of
investment in renewable electricity has made connection capacity
increasingly scarce in recent years. While policymakers face a
surplus of capacity, the projects in the connection queue are not
aligned with system needs. Based on data on connection queue
attrition, the National Energy System Operator (NESO) estimates
developers may never build up to 70% of projects in the current
queue. Stalled projects and oversupplied technologies are holding
back network capacity and queue positions from technologies needed
for Clean Power 2030 (CP30), including onshore and offshore
wind.
Long waiting times in Great Britain's queue have created
uncertainty for investors and ultimately hamper progress towards
decarbonisation by delaying the connection of the projects most
needed to decarbonise the system. Moreover, since network companies
must plan for connection works based on the current queue, the
queue is sending