The IRS issued Notice 2015-25 on March 11, 2015, to provide further guidance on meeting the beginning of construction requirements for wind and other qualified facilities.

United StatesEnergy and Natural Resources

The Internal Revenue Service (IRS) issued Notice 2015-25 (Notice) on March 11, 2015, to provide further guidance on meeting the beginning of construction requirements for wind and other qualified facilities (biomass, geothermal, landfill gas, trash, hydropower, and marine and hydrokinetic facilities). The Notice extends the date by which a facility can meet the beginning of construction deadline to correspond with the extension of Code Section 45 passed by the U.S. Congress at the end of 2014.

Background

The Tax Increase Prevention Act of 2014 (Act) extended through December 31, 2014, the deadline by which construction of a qualified facility must begin for purposes of qualifying for the production tax credit under Code Section 45 (PTC) or the investment tax credit under Code Section 48 (ITC). Previously, a taxpayer could only meet the deadline by placing the facility in service prior to January 1, 2014. Following the extension of the ITC and PTC, a taxpayer may be

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from