FERC Upholds Applicability Of CAISO Interconnection Procedures For Third-Parties Directly Interconnecting To WAPA-Owned Facilities

On November 4, 2016, FERC issued an order denying a complaint filed by HORUS Central Valley Solar 1, LLC and HORUS Central Valley Solar 2, LLC against the California Independent System Operator Corporation.

United StatesEnergy and Natural Resources

On November 4, 2016, FERC issued an order denying a complaint filed by HORUS Central Valley Solar 1, LLC and HORUS Central Valley Solar 2, LLC (jointly, "HORUS") against the California Independent System Operator Corporation ("CAISO"). In the complaint, HORUS requested that the Commission prevent CAISO from imposing interconnection procedures and study requirements in addition to those already imposed on HORUS by the Western Area Power Administration ("WAPA"). In denying the complaint, FERC reaffirmed its existing policy that generators must obtain transmission service at or beyond the point where facility ownership changes, as well as beyond the interconnection point with the wider integrated grid. Because HORUS sought to connect to WAPA-owned interconnection facilities, and those facilities in turn interconnected with CAISO, HORUS was required to comply with both WAPA's and CAISO's interconnection procedures.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from