ARTICLE · 28 FEBRUARY 2025

FERC Takes Action On Co-Located Load In PJM

The Federal Energy Regulatory Commission (FERC or Commission) on Feb. 20, 2025, initiated a review of issues associated with the co-location of large loads...

United StatesEnergy and Natural Resources

Highlights

  • The Federal Energy Regulatory Commission (FERC) has launched a review of co-location issues in the PJM Interconnection LLC (PJM) capacity market, focusing on whether the tariff needs additional provisions to address co-located loads, such as data centers adjacent to generation, to ensure grid reliability and fair costs for consumers.
  • FERC expressed concerns that PJM's tariff lacks clarity and consistency on co-location arrangements, potentially violating the "cost causation" principle and raising resource adequacy challenges due to the rapid growth of co-located loads.
  • PJM and its transmission owners must respond within 30 days to explain why the tariff is adequate or propose changes to address FERC's concerns. Interested entities may reply within 30 days after PJM's filing.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from